Filter: display incomplete cross-project successors

This task filter returns incomplete cross-project successors.

Access requirements

You must have the following access to perform the steps in this article:

Adobe Workfront plan*
Any
Adobe Workfront license*

Request to modify a filter

Plan to modify a report

Access level configurations*

Edit access to Reports, Dashboards, Calendars to modify a report

Edit access to Filters, Views, Groupings to modify a filter

NOTE

If you still don’t have access, ask your Workfront administrator if they set additional restrictions in your access level. For information on how a Workfront administrator can modify your access level, see Create or modify custom access levels.

Object permissions

Manage permissions to a report

For information on requesting additional access, see Request access to objects.

*To find out what plan, license type, or access you have, contact your Workfront administrator.

Filter cross-project successors

To apply this filter:

  1. Go to a list of tasks.

  2. From the Filter  drop-down menu, select New Filter.

  3. Click Switch to Text Mode.

  4. In the Set Filter Rules for your Report area, paste the following code:

    percentComplete=100
    percentComplete_Mod=ne
    successorsMM:projectID=FIELD:projectID
    successorsMM:projectID_Mod=ne
    
  5. Click Save Filter.